    Drawing the Lebanese National Plan (LNP)
    The Main Processes involved

    1. Identify the participants (12 days)
    2.Contact the participants (12 days)
    3.Meet and select the participants (12 days)
    4.Assemble the teams (4days)
    5.Divide the sectional plans among the teams (5 days)
    6.Explain the planning concept and study some foreign Plans
    (9days)
    7.Undertake an initial study of the Plan (36 days)
    8.The teams meet the stakeholders to evaluate the initial
    study (12 days)
    9. The teams and the stakeholders re-study the Plan jointly (36
    days)
    10.The proposals are presented to the government (12 days)